Schwartzkopffstraße
Construction-related project controlling
Auftraggeber
Telluride Architektur GmbH
Leistungsumfang
Bauüberwachung und Qualitätsüberwachung
Architekten
Telluride Architektur GmbH
Standort
Universitätsstraße 25, 33615 Bielefeld
Bauzeiten
R5: 48 Monate | R7: 27 Monate
Fertigstellung
R5: Q2 2026 | R7: Ende 2025
Project description
The building plot is located at Schwartzkopffstraße 26/28 / corner of Leipziger Straße in 14612 Falkensee. It has an area of 6,100 m² and lies within the area covered by development plan F 12 B.
The project comprises a new building with 106 residential units, an underground parking garage with 70 spaces, and 45 surface parking spaces. The angled building will consist of four full floors above ground and a penthouse level above them. It is classified as building class 5.
The entire building, including the resulting courtyard, has a single-level basement. Access to and from the underground parking garage is via the eastern wing of the building, with a short connection to Schwartzkopffstrasse.
The building is used exclusively for residential purposes. The basement levels will house tenant storage rooms, utility rooms, and communal storage areas for bicycles, strollers, and, if necessary, wheelchairs. The apartments will feature terraces on the ground floor, balconies on the upper floors, and roof terraces on the penthouse levels.
use
Residential complex with up to 5 floors
106 residential units and a total living area of approximately 7,600 m²
including the associated outdoor facilities
70 underground parking spaces for cars
45 outdoor parking spaces
geometry
Gross floor area: approx. 12,447.00 m²
Gross volume: approx. 39,845.80 m³